Hammering out the Electrical Details … its sometimes a 4 letter word!

Actual Conversation that took place at 9am Friday morning:

Matt: What about the following Electrical items:

8.1c-3, 4.32b-1, 8.0a-9

Iain: Where is that in the plans?

Matt: I can’t find them, do they even exist?

Iain: Here they are. A 5 horse power pump 3 phase 220 volt and 2 outlets

Matt: Those outlets and pump aren’t in my plans

Iain:  They are in my plans, but they are in the wrong spot

Matt: Where is the number for the engineer, I need to call him.

Get used to hearing these kinds of things when it comes to putting electrical infrastructure into your building. The work requires continuous attention to detail, and meetings between your electrician, electrical engineer, general contractor and the end-users (us)! There are lots of false starts and errors, so prepare mentally for this. Getting as much correct as you can early in the process will mean fewer change orders, which ends up saving you a lot of cash.

One of the biggest challenges we have had around the electrical work is the process. It is an inexact science and one that is full of frustration and teeth grinding. The process kind of goes like this:

  1. Pick your equipment and finalize this before anything else can start.
  2. Determine the power needs of that equipment.
  3. This is a chicken or egg thing. On much equipment, you can choose what kind of power it will take, which means you need to know what kind of power you have available. For much of your equipment you can have it made to the power you want to provide.
  4. Convey this information to the architect and electrical engineer who produce drawings for your electrician.
  5. Determining the exact location of the equipment on the floor plan. You need to have this buttoned down, so that all the information can go back up the line to everyone that needs it
  6. Make sure that all this stuff meshes with the latest version of your layout. Sometimes you electrician is working with non-current plans, which means that different tables and arrangements will result in different locations for power needs
  7. Making sure that the workers who are going to do the work know what is going on.
  8. Check back with everyone to make sure that all is ok.

Clearly, this is an inexact process. It is one that seems easy at first, but when you really look at it during the process, it is really hard. Trying to coordinate all of this is so difficult. We have had meetings where people literally leave steaming mad because they have been given the wrong information, or their workers haven’t followed the changes … there is a lot of coordinate.  Moreover, if you get anything wrong in that process you literally need to spend an hour push up and down the line to everyone else, explaining what happened and what the new plan is.

It is also important to get equipment using 600V where possible. In short, using a higher voltage makes electric motors more efficient, as there is less current needed. We are lucky in the sense that we have the power available to do this, after we are spending a bunch of money to upgrade the service from the street.

There is always going to be the stuff that people have overlooked. For instance our electrical engineer missed a couple pumps in our layout, so it was never discussed again until we found this out. When this happens, everyone scrambles to find these on the plans, and when you don’t you start to question what has happened and what you can do.

To help make this process easier, you should always try and work with professionals and engineers who are supreme communicators. You will need to be in constant contact to ensure that everyone is on the same page and everyone within their teams are also on the same page. It also helps that the electricians who are doing the work are committed to the job. If they can’t have someone at the brewery all day 4 days a week, you should look elsewhere.

Don’t forget to plan for power outages, and share the plan for renovations with everyone and every sub-trade. People need to know when power is going to be cut, when deliveries are being made and when floors are being coated. If you don’t coordinate this information, others will waste time and become increasingly frustrated with your job, potentially leading to bad outcomes down the road.

It becomes so apparent through this process that things like the electrical upgrade, floor issues, seismic needs, and sprinkler additions/installation are huge costs and enormous burdens to have to deal with. It is one of the reasons I have always told people who are interested in starting a brewery to make sure you find a space that has some of these things done. You may not be lucky enough to find one with everything completed, but the more of these major items completed, the quicker and cheaper your retrofit will be.

 

 

Advertisement

Another general update on progress and happenings at the Brewery!

It seems like I have been knee deep in the process of starting a brewery, that I have neglected to update the readers on our progress.  From the brewhouse to tanks, and forklifts to logos, there is a lot happening at the brewery, and the level of activity seems to have picked up.  In addition to the office and administrative items that have kept us busy for the past 6 months, you can add in the retrofit of our space to things to do.

For starters, Iain Hill has officially left his position at Yaletown Brewing Company to join operations full time.  For several months Iain has been burning the midnight oil after a long day at the office, and he now has the ability to focus on starting our brewery, which is amazing on many levels.  Finding a brewery (and in my case a business partner and equal) is a huge step in the process of starting a brewery.  Its one thing to be a home brewer like many of you.  You understand some of the components of brewing beer, and you have experience with the lingo and terminology, but its entirely another thing to be in charge of a commercial brewery.  With a qualified partner, the beer we make will be of good enough quality that it will offer us a chance to have success.  If you want to follow Iain Hill on twitter, his account can be found here.

We have sent out tenders for our warehouse to electrical and mechanical contractors.  This has been a bit of a process for us.  When you apply for building permit, you have a sense of where things are going to go, and this is reflected in the drawings your architect prepares for you.  However, when it comes to the technical details of these aspects of the brewery, you engage with mechanical and electrical engineers to complete these drawings.  Getting the details correct on these drawings is critical to getting accurate quotes from trades people that will be doing the work.  If you hand over a set of drawings for tender and they change immensely, you will get dinged for additional expenses throughout the build-out phase.  My advice would be to push ahead with these drawings at every opportunity, so that when you get your building permit, you are not at a standstill like we were.  We will literally lose a month from our possible start-date as we were not ready the next step.

Doing things in the brewery that don’t need a permit is also something that is very important.  We have decided to paint the inside walls of the brewery with a marine grade paint, to keep mould from becoming a problem.  Well painting a house is a job, but painting 6 metre high walls in a brewhouse that is 9,000 square feet is a little bigger of a job.  This is something that we really should have started earlier as well, but given the delays in getting started with the rest of the work, we will have this finished within the week.  Once the walls are painted we can move forward with cutting floors open, and getting our brewery ready for building.

If you ever need advice on buying a forklift, I can tell you that we had a great experience and I would love to share it with you.  At the end of the day, when you are spending so much money on everything at a brewery, trying to save money on items like forklifts can go a long way.  We managed to save about $5,000 against our budget, and while that will get sucked up quickly elsewhere, the point is you need to save money when and where you can.  We had a budget of $10,000 for a forklift, charger, and man cage (for doing work on the ceiling of the brewery).  After about 30 hours of work, research and seeing what the options were, we purchased an electric forklift that will hopefully meet all our needs for now and into the future.  Sure we might have to spend money on repairs, but we are not going to lose much money on this machine as it already has depreciated to nothing.  If you are looking; side shift, electric drive, 40 inch forks, 180 inch lift height, and a smart charger that is compatible with your machine are all must haves.

In terms of the voting on our logo, it looks the voting has ended up at 50-50!  After all that, we have a divided opinion on what we should be going ahead with!  As such, Iain and I are going to meet and make a decision on what we should move forward with.  We look forward to making a decision so that we can move forward with other aspects of our marketing.

Our landing page for the website should be up and running in about a week.  I know there has been delays (like everything it seems), but we hope to have an interesting landing page that will continue with giving everyone a sneak peak into starting a brewery and our operations.  More to come on that front shortly.

I have found an individual that has helped me with odd jobs at the brewery so far, and I would recommend to anyone else who is looking at starting a brewery, to find someone with some technical background in general labour … what I mean is find someone to help you that can do some electrical, plumbing, painting, heavy lifting, etc.  We have found a man to help us, and he has been a saviour for us.

From an equipment standpoint, we have ordered our brewhouse and we are very close to ordering our packaging equipment and conditioning/fermenting tanks.  We are trying to determine exactly packaging equipment we want, as the choice we make will help determine our entry point into the market.  If you go cans, you come across as more of a middle of the road company. If you go with bigger bottles (650ml) then you come across as more of a craft operation.  So we are wrestling with what exactly to do, and I hope we can make a decision in the next week.  As for the tanks, we are grinding the suppliers on their price, and hope to get our ideal package within our budget.  We think it is better to go a little bit smaller on the tank farm, knowing that you may run out of capacity quickly, than spend all your money on equipment and have very little left over for everything else.

Thats it for now.  Should there be anything else you want an update on, as always, let me know and I will include it for my next blog.