Category Archives: Brewhouse

26 Days to Go …. Inspection, We’re Hiring (Soon) and Marketing

On Friday of last week, we had our contact from the Liquor Control and Licensing branch pop in for an inspection.  This is a super important moment, as they are essentially the eyes and ears of the government arm responsible for allowing us to make beer (a manufacturers licence).  Our inspection went well, at least we think, and we should be getting some answers this week, so we can legally start brewing beer in the next week.  That is a big if, and should we get this license, we are on schedule for a early December opening.  If not, we can kiss goodbye an early December opening.

Iain has promised he can brew beer that takes about 3 weeks to go from brewhouse to glass, though it will be a lot less time than he hoped, it is possible.  We are definitely going to swing open the doors and have a beer line-up that is not necessarily reflective of our exact wishes, but we wouldn’t be the first or last to do this.  Over time, we will brew a larger armamentarium of beers that will make beer lovers and newcomers to craft beer happy.

With this eventuality, we have many other things to do, not the least of which is to hire staff for the front of the house.  We expect that we are going to need to hire about 10 – 15 people to work in the tasting room, depending on the number of shifts each person is looking to work each week.  If you are interested in working with us, prepare for a call for resumes in the very near future.

We are also busy working on the marketing material and information for our brand.  While many of the major items have been decided on (like logo, can design, business cards, beer glasses, growlers, etc) there is a seemingly endless list of small things to do.  Items like pricing of all items, food in the tasting room, an artists call for submissions, meeting with neighbours who may visit our brewery, sales calls to resellers, video, photography, getting exterior signs fixed, etc.

With all this going on, it is hard to find the time to help out in the brewery very much of late.  Both Iain and I have been contributing less and less to the job of completing the work in the brewery, and more on the task of getting ready to make and distribute beer.  I know my time in the brewery is down to about 25 hours per week of hard labour, and Iain is even less as he is spending time cleaning, preparing, turning valves …. god knows what the heck a brewer does, but I am sure it is all important stuff.

Anyhow, lots of stuff to do, so I am going to get cracking at it ….

34 days out …. sneak peak at our Layout

Not much to say on this post.  I am a little foggy this morning, and needing to get 2 blog posts out as I missed one from yesterday.  The first post today will be around the finalized layout and look of our tasting room, and the exterior elevation of our space

We agonized for months over how exactly to design and locate the entire production and front of house spaces.  There were likely 5 or 6 meetings with our architects to get this correct, and hopefully at the end of the day, we got it right from a production standpoint, but also a tasting room standpoint.

Some keys about the front of the house:

  • The tasting room has a direct connection to the brewhouse, where most of the fun stuff happens in brewing beer
  • The art gallery is directly connected to the tasting room, allowing people to view some artwork while they visit the brewery
  • We have 2 long communal tables, which is a direct result of bring people together through beer.  If you want to come to our brewery and sit quietly on your own, you might have a tough time
  • We will have lots of natural light.  There are about 14 windows across the front, that will provide heaps of natural light into the space
  • There is a moderately separated retail area from the tasting room, which will allow the patrons of each to not interfere with each others good time
  • The lines from our serving tanks to the tasting room are crazy short, as the cooler is right there
  • The front of the house has really high ceilings, something you can’t really see in the drawings, hopefully making the space very interesting and welcoming

As for the exterior of the building, not much to do other than clean it up, repaint and put a few new doors in to make the building secure and a little more functional.

There was a lot of found value in the space, which we have tried to salvage and add to in a positive and authentic manner.  Both Iain and like things that are authentic and interesting, and we hope to have created a space that is, if nothing else, both of these things.  We hope you pop-in and say hi the next time you are in the area.

Architectural drawings Oct 31.2014

 

38 Days Out … Boiler Installation and Inspection

Don’t drop the ball on this!  There are a lot of details and a lot that has to go right.  Most importantly, don’t overlook the cost on this.  When you look to purchase a boiler, expect a good chunk of change.  I believe our boiler cost about $13,500 which is only part of the cost.  Installation of the boiler can be almost double the cost of the boiler.  A few best practices that may or may not help you:

  • Get the right size boiler for your operations:  Anything too small or too big will give you headaches, additional cost, take up too much room, not have enough/too much power, etc.  This takes some planning, projecting and ultimately guessing at the end of the day.  We ended up getting a bigger space, so we figured we needed a bit bigger of a boiler to handle future production (we hope!).
  • Put it close to where you need the water:  At first I didn’t understand why Iain wanted to put our boiler so close to the brewhouse, as it was in an awkward spot.  Having seen all the pipes and connections a boiler has, and the incredibly thick gauge of pipe connected to it, put the boiler as close to the brewhouse as you can.  The further away you put it, the dollars and cents will quickly add up.
  • Pre-Inspections are important:  We had a company come in and do a pre inspection to make sure we were putting it the correct distances away from other objects, it was positioned right, and we would be able to get our eventual inspection passed.  This was money well spent as they gave us some good advice that helped us down the road.  On their advice, we ended up rotating the boiler 180 degrees and thank god we had them tell us this, as otherwise, we would have failed our inspection and re-connect all the pipping at a huge time and financial cost
  • Inspection required before you fire it up:  Before you can’t start using your boiler, and that means start cleaning and sanitizing your equipment, until you pass your inspection.  Period. So make sure your boiler is ordered, delivered and installed well ahead of time.  If not, you will be leaving no margin of error

So that is my little advice on a boiler.  Our mechanical contractor Nathan Pulice was incredible throughout this process, but especially for us during the boiler install.  I would highly recommend for anyone who needs any mechanical, plumbing, HVAC, etc to contact him … especially if you are starting a brewery in Vancouver as he has superior knowledge about everything.  Nathan can be called reached at (778) 227 8219 or visit his website here http://www.meridianplumbing.ca.

Tomorrow I will talk about finishing of the front of house.  There is a lot of navigation required for this, and a few best practices to share.

General Ramblings

A lot of the things we have been planning for sometime now are taking shape.  The big decisions we had to make early on have all been made, and now we are left to make them all fit within the scope of this project, which is changing a daily basis.  As such, things like tap location, size of custom cabinetry, location of bar sinks, and hundreds of other little decisions need to be looked at.

We have made many errors both big and small along the way, as making so many decisions is bound to result in a bad decision or 2 ….. or 20!  So here are the mistakes we have made that come to the top of my mind, and things you should be mindful of not doing.

  1. Make sure you agree to delivery dates for equipment and services provided to your brewery.  If you don’t have specified drop-dead dates, you can’t hold people to a timeframe in getting things done.  For example, if your website needs to be created by June 1st, but you don’t have this in your contact with your web designer, then you are left with no recourse should things take longer.
  2. The marathon of this is truly day in and day out a grind.  I love what I am doing, and it is a passion and dream all rolled into one, but it is still a grind.  The first 6 months seem to go by quickly, and your energy reserves are used, the next 6 months you have moments of highs and lows, and then the next 6 months hit.  I would say this is where we are.  We don’t celebrate our accomplishments enough, we are knee deep in financial duress, and we are about 2-3 months away from making any money.  Take 1 day off a week, as it will do your mind good.
  3. Its better to have stuff arrive when you need it, not before or after.  This is virtually impossible, but getting a big piece of equipment early is in a way just as bad as getting it early.  Get your stuff delivered when you need it, and shade a little to the earlier side of things.
  4. There is an endless amount of forms you need to fill out for the Government, so always keep on top of this.  I try to spend a couple hours a week reviewing our progress and making sure we are doing all that we can to keep these things moving forward.
  5. Schedule meetings wit your partner.  I can’t tell you how many times my partner and I try to meet about something and it gets interrupted or cut short because of something else.  We are realizing it might be best to have meetings elsewhere that are important.  Planning the business is more important than working in the business
  6. Finding time to do social media is the hardest thing some days.  When you are working on building a brewery, your free time evaporates and days just cruise by.  Always find time to connect with people on social media.  For some that is doing it as the day goes on, and for me that means doing it twice per day.  We have learned so much from others, and connected with so many great people, it would be a shame not to have done this.
  7. Include your landlord in decisions that effect the building.  If you have an amazing landlord like we do, they will want to be a part of things, so it is important to let them have some say.  After all, it is their building and your business is their business.
  8. Always have a plan B ready for action, especially when it comes to your financials and marketing.  Getting stuck with one idea, or one way of doing things is a real challenge in any aspect of this process.  It evolves so much, that it is much better to wave in the wind like a flag and go with the flow.
  9. You will need money, lots of money, and you will likely need more as the process goes on.  If you think you are different than everyone else who has started a business, or undertaken a massive renovation, then do so at your own peril.  We thought we would be good after 4 or 5 revisions to our budget, only to have the wrench of a delay resulting in us needing more money.  My advice would be to research as much as possible, and leave a bucket of money with about 15% of your overall budget to get to day 1 so that you can mitigate these risks.
  10. Marketing needs to represent who you are.  Since we are a team of 2, it is harder to get this right, as we are both very different in what we like.  Also, we wanted something other than what represented who we were for some time.  Once we decided to go with our gut, we found a path to happiness and cool branding, representative of our beliefs and opinions.
  11. If you are having a tasting room like us, the front of the house is a big enigma that is full of unknowns and expensive items.  Walk carefully through this minefield.  We messed up tap locations, counter top height, layout, approval process, etc.  A lot can go wrong so make sure you think this through.
  12. Don’t forget about these electronic items/systems:  POS ($5,000) AV ($2,500) Security system ($1,500) and CCTV ($4,000).  They add up to a lot, but we couldn’t imagine not getting these things right.  Also, try to include these items on your electrical contractors scope of work early on, as it will save you $$$.
  13. Spend too much money on non-critical things.  Don’t spend a lot of money on a forklift, but get a used one.  Don’t pay any of your carpenters to clean up at $55 per hour, do it yourself. Don’t get a bin until you are ready for it, do a couple dump runs on your own.  You get the idea.

I am sure throughout today, I will make 10 decisions with my partner, 7 of which we get right, 1 we are not so sure about and 2 that are wrong … only we won’t know it until some later point.  The point is sometimes you need take your time and make the right decision, and others you need to make any decision, just make one immediately to keep things moving forward.  The key is to think about when key decisions need to be made, and factor that into your approach.  If a decision doesn’t need to made, take a day to sleep on it.

I am sure I would be able to add about 10 more things to this list if I had the time or more mental horsepower right now.  Hopefully you can add more to this list via the comments below. Thanks for reading and until my next entry.

50 days out update … this may be my last

For a long time this blog has been a pleasure to write.  I enjoyed going over my notes of things, and putting that into the greater community.  The response and positive energy I received along the way was amazing and helped encourage me to continue writing, especially at times that I was either tired or busy (which seems like all the time).  About 2 months ago, the blog started becoming more of a burden, as the amount of time I spent working at the brewery and on my computer increased weekly.  Add in a complete gut of a house my wife and I purchased, and all of a sudden all of my free time evaporated.  Poof!

So given the state of my personal and professional life, and for the sanity and health of my family life and longevity in business, I have made the decision to free myself from the burden of having to write this blog.  Rather than see a note pop up in my calendar every Sunday night to write a blog post, I have removed the reminder from my calendar, and will let things run their course.  For those of you who follow my blog with regularity, feel free to email me with questions you have.  Also, I promise to continue taking my notes, and should I not find the time to blog about this process until the day we open, I will catch up afterwards.  That way this process will be complete.

So for now, this last blog post may actually be 4 or 5 posts rolled into one, as I update all the different aspects of starting a craft brewery that happen about 2 months out from opening.

Brewhouse:  Ideally, you will have your brewhouse arrive about 60 days prior to opening,  Definitely make sure you put any coatings on your floor.  Also make sure you have your installation procedure decided well in advance.  I am sure by this point you know what you are doing, but it had to be said.

Tank Farm:  Big or small, your tank farm should also be in about 60 days prior to opening, most ideally just before or just after your brewhouse goes in.  Be sure to have your Glycol system scheduled for installation, which needs to be done before you can move your tanks into position.  Also plan for your unloading of tanks for the truck and installation into position.  This can be a really finicky process that needs an experienced touch.

Kegs:  You ideally would get these delivered with about 30 days to go until opening.  Getting them delivered too soon (like we did) means you lose valuable real estate in your brewery that could be used for some other things.  More on use of real estate later.  At the end of the day, get the kegs early, but not too early.

Electrical:  If you are getting major upgrades as we are, make sure you the majority of the work done as soon as possible.  Don’t use an electrician who doesn’t commit to getting things completed by certain dates.  More important than saving a few thousand is someone who works with your schedule, and is always ahead of the game.

Mechanical:   I could literally write the same thing again for this heading that I did for electrical.  Make sure the work gets completed when there is the space and option of doing it.  Never wait for stuff to get done.

Marketing:  Holy crap, the marketing becomes a beast by this point in time.  The decisions you make mean the brand you are creating is formally taking shape.  The big important decisions are long complete, but there are a million and one details.  And the saying goes that the devil is in the details.  Some of the important balls in the air right now are:  Website, content for website, business cards, merchandise, increasing social media presence, glasses, sell sheets, coasters, keg labels, etc.  I would say marketing at this point will likely be taking you about 15 hours per week if you are doing anything similar to us.

Tasting Room:  This is one of the last things to get finished, as the production equipment needs to prioritized, but certainly by now the tasting room is well on its way to completion.  You are definitely making the finer decisions now on this.  Things like designing tables, finishing of walls, merchandise area, etc are all needing decisions to keep things moving forward.  We are about to start on construction of a bar, and I can tell you that there are a lot of factors that go into putting this together, and I promise to one day blog about it.

Accounting:  By now, I hope you have figured out a system for managing your books.  It is easily something that gets left, and before you know it, your GST reporting is due, and instead of a few hours work, you have 3 days worth of book keeping to catch up on.  Dave at Powell Street Brewing gave me the recommendation early to do your accounting every 2 weeks, and while I haven’t yet gotten to that frequency, I can see why he recommends it.

Organizing Trades:  We are sooooo thankful we have a general contractor.  Trying to organize and manage the schedule is a full time job, and one that we couldn’t have imagined not having the support of Graham Disher and his fine team.  They have helped us immeasurably every step along the way, and we are firm believers that paying someone to help is the best move we made.  Organizing trades and their schedule is so important as you come down to this point, as when things get done (or not) has a cascade on all the other things that have to happen after.  Any delays means a delay to every subsequent job.

Cold Room:  After going through the building of a cold room, we are really happy we did this, but man, we think getting a prefab cooler would be a lot better choice next time.  I know we will get exactly what we want and need, but the process of building a cooler is an expensive one, that takes a lot of time, and draws people away from other tasks they could be completing.  Depending on your space and the size of a cooler you need, strongly consider a pre-fab.

Cash Flow:  Hopefully you are meeting your budget, but most likely you are not.  This is where you need to make a decision if you have investors.  Do you take a bigger loan to cover your shortfall or do you raise more money.  In about another month we are going to be pressed with this decision, as we will be out of money.  Managing your cash flow until you get open is the most important part of this process and one that you need to keep on top of constantly.

Government Stuff:  Make sure you keep on top of all the interactions you have with government.  You can easily drop the ball on this one, and the resulting error could be catastrophic to your business.  In British Columbia the government has a website that itemizes all the things you need to do and I suggest you refer to this consistently.

Hiring of staff:  About 50 days out you need to figure out your staffing situation, and start getting ready to hire people.  For us that means people in the brewery and also in our tasting room.  We have been dragging our heels on this one, so do as I say and not as I do.

Other General stuff of note:

Use of Real Estate:  During the process of building a brewery, as you reach about 2 months out, your space is a mess.  There are a hundred things inside your brewery that are at various states of completion, which means there is a lot of stuff sitting in different areas.  For us, even though we are in 9,000 square feet, we are running out of room to put stuff.  We have kegs, barrels, packaging, tanks, wood, plywood, insulation, drywall, tools, work stations, etc taking up space all over.  My advice would be to work on being organized as best you can from day 1.  Don’t let the mess and organization become an issue, as it can overwhelm you.

Manage your Expectations:  I am someone who was raised by a very European father, who was adamant that we were never late for things.  While I am not 100% on time, I do think that making a scheduled deadline is important.  When it comes to something as complex as starting a brewery, just plan for 7 months of building if your size is 6,000 square feet or smaller.  And if you are over 6,000 square feet like us, plan for 8-9 months of building.  I know you will always be able to point to examples that go against this timeline, but do so at your own peril.  Just expect things to go wrong and problems to come up that add time.

Manage your sleep and stress:  For me, a lack of sleep goes hand in hand with being more prone to stress.  To give you an idea, right now I am working about 75 hours a week.  I easily work 12 hours per day 6 days per week, and I do try and take a 1/2 day off on the 7th day of the week.  The 2 things that I hate to lose is my sleep and my exercise.  If I do, I get more stressed, grumpy and unhappy.  So for me, I need to continue to exercise (a lot less intensely with all the physical work at the brewery) and get my 6.5 hours of sleep a night.  Any less than that, and I start to burnout.

Celebrate:  If you don’t stop once and while to celebrate the process, you will miss out on the process of following your dreams.  We are all following our dreams when you start a brewery, and if you don’t take a moment to recognize this, then the process will be less rewarding.

Decisions are now to save time or save money:  The process of making decisions has gone from really taking your time and agonizing over the details, to one that is marked by a lack of research and a plethora of going with your gut.  We are still trying to save money as we always have, but now there is a healthy dose of getting decisions made.  In fact, I would say the first question we usually ask is which option is the quickest?

Stay connected with your partner(s):  It is really easy to divide out a job and then not keep in good enough contact with your partner.  We are all guilty of this, but make sure you take time every day to speak with anyone that needs to be part of a decision.  It also helps to have a master sheet schedule, as I have talked about before, so you can itemize the decisions you need to make, who is doing it, and when the drop-dead date is.

Hopefully, with all this stuff going on you can understand why I am going to blog if and only if I have time over the next 50 days.  My to do list is insane, and I can’t keep up with all the items that need decisions.  I hope you understand!  As such, I am going to take off and get some of these things done.  Until next time …. and always email me with any questions.

 

 

 

Best Practices: Tank delivery

After having received our fermenting and conditioning tanks, there are some things that we learned, and I would like to pass them onto anyone else that is ever going to receive tanks.  There is a lot to know, but basically it comes down to preparing properly and having someone to help.

We ordered our fermenting and conditioning tanks from China, so ours arrived in the least convenient manner possible.  By shipping container, at a random time during the day.  This was the start of the challenges, but thanks to an amazing person, we quickly learned how to get everything off the containers in a safe and efficient manner.  Here is my list of things to do and not to do.

  1. Plan the day ahead of time:  Duh!  Just make sure you tell all the other trades what is happening, and plan for guests to not show up, even though it is a really exciting day.  It is not one that you can socialize on or anything else.
  2. Work with Customs Broker:  Don’t leave this to the last moment.  Make sure you have someone that can help you get the shipments into your port of entry.  We selected a company about 1 month ago, and it was a very good choice.  If you are BC based, let me know and we can connect you.
  3. Bring in other shipments into Canada ahead of this shipment:  Order something, anything as if you have a history of bringing shipments over $2,000 into Canada, then customs is much less likely to open one of your containers.  Why is this an issue?  If they open any containers, they charge you an inspection fee and it can run over $1,000 per container they look at.
  4. Rent a second forklift:  Having a second forklift made our job a lot easier, as one forklift could focus on bringing the equipment into the warehouse, which left us with another that could support or help out where needed.  Get the second forklift with long forks, and get a pair of fork extenders for your own forklift.
  5. Get strapping, wood and other materials ready beforehand:  You should have lots of cardboard on hand for putting between the forks and any tanks, wood pieces for resting the tanks on, straps for securing the tanks when offloading, etc.  All of these things will make your day go a lot smoother.
  6. Have your team all ready and available during the day:  Even if 2 or 3 of you are unloading the stuff, everyone else who is around should be ready to help out as needed.  We had a few tricky moments, and if we didn’t have 5 or 6 sets of hands around, it would have been a lot more difficult.
  7. Think about a professional:  Lucky for us, we employed the services of someone who works for Ripley tanks.  This person was the only reason we got through the day.  He has unloaded heaps of containers in the past, so his knowledge about the process was more than invaluable.  He led our team, and he made things go quickly and easily.  We had only one mishap and that was due to driver error.
  8. Plan for a long day:  It took us 12 hours to unload 20 tanks, which ranged in size from about 15HL to 30HL.  If your tanks are smaller, it might go a little quicker, but we averaged about 2-3 tanks per hour depending on the size.
  9. Work efficiently for cost savings:  We received 2 free hours per truck that was delivering the tanks.  If we went over, we would have to pay.  So be quick and get things off and move on.  There was a time that we had about 8 tanks sitting in our parking lot.
  10. Plan for the wrong order of tanks:  We received our tanks in an order that wasn’t ideal.  The result, we had to have a plan of where to put them, and how they would go into our space.
  11. Get your Glycol and Floor Coatings completed ahead of delivery:  Our tanks are still in the same position as when they arrived, as we don’t have all our floor coatings complete, and our glycol system is still a work in progress.  If we had these things complete, we could easily  start putting our tanks in their final position.  My advice, plan ahead and get this stuff done as quickly as you can.
  12. Make extra room:  You will need twice as much space as the tanks will occupy, for storage, moving them around, placing and re-placing.  So the day before, make sure you create this space.

I am sure there are other things we did and didn’t do, but I can’t think of them right now.  Hopefully this list helps, and if you have specific questions, please don’t hesitate to email me.

10 BBL Brewhouse for Sale

During the process of starting a brewery and writing a blog about starting a brewery, I have met and continue to meet many fascinating people.  These are people who are willing to do as others have before us, and risk everything they have achieved in order to start a business.  You see all sorts of personalities and business ideas come through, and they run the range from amazing to crazy.  Some people have leased a space without even having a business plan, and others have strong marketing backgrounds, and others lots of home brewing but no commercial brewing experience, etc, etc.

One of the groups that I have recently met purchased a brewhouse with the hopes of using it for their own purposes, but their circumstances have changed and they are looking to sell this.  So there isn’t much more to say than this:  If you are looking for a 10BBL brewhouse with all the parts and potentially someone to help consult with you, send me an email, and I can connect the two of you.  I don’t know the price, and I don’t even know all the equipment that is included in this set-up, but from the quality of the individual who is selling it, I am sure it will work out well.

If anyone you know is looking for used equipment, please pass along this information.  I know it is very difficult to find equipment in the marketplace, given the growth of craft beer throughout North America.  Having  an inside line like this can be a huge help in starting a business and saving cash on the most important part of your business.

As always, send any information to:

startingacraftbrewery@gmail.com

 

Hammering out the Electrical Details … its sometimes a 4 letter word!

Actual Conversation that took place at 9am Friday morning:

Matt: What about the following Electrical items:

8.1c-3, 4.32b-1, 8.0a-9

Iain: Where is that in the plans?

Matt: I can’t find them, do they even exist?

Iain: Here they are. A 5 horse power pump 3 phase 220 volt and 2 outlets

Matt: Those outlets and pump aren’t in my plans

Iain:  They are in my plans, but they are in the wrong spot

Matt: Where is the number for the engineer, I need to call him.

Get used to hearing these kinds of things when it comes to putting electrical infrastructure into your building. The work requires continuous attention to detail, and meetings between your electrician, electrical engineer, general contractor and the end-users (us)! There are lots of false starts and errors, so prepare mentally for this. Getting as much correct as you can early in the process will mean fewer change orders, which ends up saving you a lot of cash.

One of the biggest challenges we have had around the electrical work is the process. It is an inexact science and one that is full of frustration and teeth grinding. The process kind of goes like this:

  1. Pick your equipment and finalize this before anything else can start.
  2. Determine the power needs of that equipment.
  3. This is a chicken or egg thing. On much equipment, you can choose what kind of power it will take, which means you need to know what kind of power you have available. For much of your equipment you can have it made to the power you want to provide.
  4. Convey this information to the architect and electrical engineer who produce drawings for your electrician.
  5. Determining the exact location of the equipment on the floor plan. You need to have this buttoned down, so that all the information can go back up the line to everyone that needs it
  6. Make sure that all this stuff meshes with the latest version of your layout. Sometimes you electrician is working with non-current plans, which means that different tables and arrangements will result in different locations for power needs
  7. Making sure that the workers who are going to do the work know what is going on.
  8. Check back with everyone to make sure that all is ok.

Clearly, this is an inexact process. It is one that seems easy at first, but when you really look at it during the process, it is really hard. Trying to coordinate all of this is so difficult. We have had meetings where people literally leave steaming mad because they have been given the wrong information, or their workers haven’t followed the changes … there is a lot of coordinate.  Moreover, if you get anything wrong in that process you literally need to spend an hour push up and down the line to everyone else, explaining what happened and what the new plan is.

It is also important to get equipment using 600V where possible. In short, using a higher voltage makes electric motors more efficient, as there is less current needed. We are lucky in the sense that we have the power available to do this, after we are spending a bunch of money to upgrade the service from the street.

There is always going to be the stuff that people have overlooked. For instance our electrical engineer missed a couple pumps in our layout, so it was never discussed again until we found this out. When this happens, everyone scrambles to find these on the plans, and when you don’t you start to question what has happened and what you can do.

To help make this process easier, you should always try and work with professionals and engineers who are supreme communicators. You will need to be in constant contact to ensure that everyone is on the same page and everyone within their teams are also on the same page. It also helps that the electricians who are doing the work are committed to the job. If they can’t have someone at the brewery all day 4 days a week, you should look elsewhere.

Don’t forget to plan for power outages, and share the plan for renovations with everyone and every sub-trade. People need to know when power is going to be cut, when deliveries are being made and when floors are being coated. If you don’t coordinate this information, others will waste time and become increasingly frustrated with your job, potentially leading to bad outcomes down the road.

It becomes so apparent through this process that things like the electrical upgrade, floor issues, seismic needs, and sprinkler additions/installation are huge costs and enormous burdens to have to deal with. It is one of the reasons I have always told people who are interested in starting a brewery to make sure you find a space that has some of these things done. You may not be lucky enough to find one with everything completed, but the more of these major items completed, the quicker and cheaper your retrofit will be.

 

 

The Cooler

Busy doesn’t even begin to describe our life right now.  We are so busy trying to get things organized with regards to all aspects of this brewery, it is literally starting to make us crazy.  We are dealing with it the best we can, but it seems we are taking less and less time to make constantly more important decisions.  There is just no time to think, it is more of a reactionary process now.  One of these things we have been reacting to over the past few months is the cooler.

Early on in the process of building a brewery, you will need to make some decisions around the cooler.  Most likely, the first will be where the heck to put the thing.  There is a bunch of factors in making that decision, like if you will have a tasting room, where are your shipping docks, how high are your ceilings all over the warehouse, how much space do you have, etc.  Generally speaking, if you are going for a model that has a tasting room, and you are planning for some production, make sure you put your cooler very near the tasting room, and make it big enough for whatever your beer sales are at year 3.

After you pick out the location, things start becoming more and more detailed in your decisions.  A big one is whether you want to have your cooler pre-fabricated or built on site.  A pre-fab cooler is a quicker option, but you may not get exactly what you want.  Also, depending on the size of the cooler, you may need to build a box around it to support it.  There are some coolers that are not meant to support any weight above them.  If you build your own, there are engineering costs, and the time and effort of putting the things together.  The bigger you build it, the more the costs for everything like labour, materials and professionals.

We also did a few extra things in our cooler that has made it more expensive, but will enable us to have a more functional cooler, and one that works better with our situation.

  • We insulated the ground beneath our concrete to R20.  This was an extra few thousand dollars to do this in extra digging, dirt removal, labour and materials, but we hope the energy savings will benefit us moving forward.  Cool air falls after all, so we thought best to insulate the floors.
  • Since we poured new floors underneath the cooler, we put in drainage.  I think Iain would say that drainage is a must in a cooler, but it can be a time consuming and difficult process.  We just decided to put all new concrete down, so we didn’t have to worry about these things …. we just did it.
  • And since we put in new floors we also put a slope on the concrete so water would run to the drains.
  • Make sure you put footings all around the cooler for the walls to sit on.  Since the cooler will be wet and damp, you should avoid having the walls touch the ground.
  • We made our cooler structural, so that we could store boxes, pallets and other stuff up top of it.
  • Don’t use drywall on the inside of your cooler … even the stuff that is rated to handle wet situations.  You can talk to Dave Varga about that one, as he told us at 33 acres they want to rip it all out.  Use marine grade plywood.
  • If you have any breaks in your moisture barrier, you will moisture in your cooler.  So plug these holes.
  • Use a big door for your cooler, and have a second man door.  The bigger your door, the easier it is for a forklift or pump truck to move pallets in and out of the space.  You want to try and avoid turning on the inside of your cooler with the forklift.  Our cooler is about 25 feet wide, and our door is about 18 feet wide or so.
  • Use a little man door to walk in and out of to avoid needing to open the big door to get something little.
  • We incorporated a cooler very close to our tasting room, so that we could have really short runs for the beer we will have on tap.  Again, Iain could tell you exactly why we did this, but all I know is that it will save us a lot of headaches in the future.
  • We will have jacketed tanks, so this means they will not be inside the cooler.  This frees up a lot of space and will allow us to store finished product in a cool place, ensuring it lasts longer and stays as fresh as possible.  This goes back to making sure your cooler is big enough.
  • Retail doors are important.  One thing we like about Bomber Brewing is that their cooler is also a place to put packaged product.  So you can grab a 12 pack of cans directly from cooler doors and purchase them on site.  This means you don’t need to get a separate cooler to do this, saving energy and costs.
  • We are placing 4 double stacked 15 hectolitre tanks in the cooler for holding our beer.  This will mean we don’t have to change loads of kegs for our most popular beers.  We have been told how much of a challenge this is, as tanks of your most popular beers can run dry 3 or 4 times a day.

All of the decisions around this cooler are pretty much made, so it is just a matter of implementing what we have planned.  The last decision we have to make is whether to use spray foam insulation versus standard insulation.  There are major differences, not the least of which is price and ease of install.  Like every other decision we have made, I am sure the answer will come to us in time …. and hopefully soon.

That is about all I can think of when it comes to our cooler.  For us, we definitely underestimated the spend on an engineer for this, as there is much to figure out when you are building walls that are 14 feet high, and span a 25 foot length.  There are lots of plates and reinforcements you need to install so that this thing will stand through worst case scenarios.

Have a few questions that I am not thinking of???  Send them along and I can surely help you out.

 

90 Days Out?!?!

Give or take a few days, we are about 90 days from opening our brewery, and the list of stuff we need to do and decide on seems to have only gotten longer and bigger.  When you are about 90 days out, the major decisions have been made, but there is still a lot of decisions to be made that can change the outcome of this process.  Let me recap where we are in the process so you can see what needs to be done.

We have finished all the in-ground mechanical work.  So plumbing, running conduit, reinforcing of concrete for tanks, upgrading floors, pouring curbs, trade waste interceptor, flow meter, drains, and a bunch of other stuff has all been decided.  That means we have made decisions galore to get to this point.  Having someone on board like Iain Hill, who has experience in starting a brewery is huge.  He has been down this road before, and knows what is a need to have and a nice to have.

We are currently getting all of our walls built  for the brewery interior, and while there is little work for the partners to do, there a lot of office work for us to complete.  The work of our carpenters is really important, albeit very slow.  Building walls and making sure they are square, level and plumb is tedious work at best, and requires a crew to make sure it all goes well.  While construction is at this point, there is a lit of other things we need to accomplish.

Most of the items revolve around the front of house.  We need to take the bar from conceptual to design.  That means we need to know what we are putting in the bar, the dimensions of those items, where we want shelves, drawers and other items, where does the sink go, where the POS goes, how many POS, etc.  All of this information then gets meshed with the best practices of our architect and then created into a set of drawings for us to send out to tender.  Once we choose who makes them, they then need to be manufactured, delivered and installed. The whole process seems to take about 12 weeks, so timing is of the essence.

While all of this is happening, our mechanical contractor is running pipes overhead, to and from all the important locations in the brewery, and our electrical contractor is upgrading our power and making things happen from an electrical point of view.

Now is also the time to start deciding on exterior colours and upgrades as we are nearing the time when this will need to be completed.  We have been working towards getting our sign ordered and it has been a bit of a mess in knowing who to use and what to get.  Our exterior sign is old and is going to cost a bunch of money to repair.  So do we pick something that is going to hold for a couple years, until we have cash to really replace it, or do we make the big upgrade now?  We are leaning towards saving the money as we have made a mess of our budget.  Saving money when we can seems really important.

All of our major equipment has been ordered, and we are just looking for odds and ends to round out the brewing side.  Iain is busy working on the draft system/growler fill area, and what we are going to do and how all that is going to come together.  I can’t say I know much, but what I know seems to confuse me.  Looks like we can go with a few different options, and each has pro’s and con’s, which I can fully describe at this time, as I haven’t been working in that bucket.

The schedule which I spoke about in my last post, gets changed almost daily, and drop dead dates are really important to adhere to.  So is having regular meetings to stay on top of all the decisions that each partner is making.  For instance, I have the exterior sign, website construction, marketing buckets to figure things out in, and Iain has the bar and equipment buckets to work in, and before you know it, you can make decisions in your own mind without talking to the other person.  So you seem to spend hours writing emails and following up on things with your partner, just so they know what they heck is going on.  A bit tedious, but sooooo important.

From here, we have lots more to do, and while we are very close, it feels in a way like we are so far away.  Its hard to think that in the next 90 days, all that is our space and mess of things, will get cobbled together into a usable brewery and tasting room.  Sometimes it still doesn’t feel like it will happen.