Success … Building Permit has been Granted!

For the past week I have had my head down, working on our accounting and driving ahead a bunch of projects that are in need to time and attention.  So this blog has been something that I keep thinking about, but couldn’t find the time or the energy to put towards it.  While we were busy with our heads down, we received some great news:  Our building permit was approved and we are good to start trucking ahead with construction.

This sounds great on paper, only we thought the process of getting a permit would take a little longer, so we don’t have all our sub-trades in place and need to refine a few more of our plans.  Given this, we hope that construction will begin on April 1st, so that we can be open sometime in very late summer or very early fall.

My advice to people who are going through the process of starting a brewery, or any other business for that matter is this:  Don’t take your foot off the gas pedal.  When you lose focus and when you lose the drive to push things ahead, small delays can have a cascade effect on the process.  For example, our dithering on a few specifics around the brewery and tasting room, which didn’t seem like huge delays at the time, effected a bunch of other items.  It delayed our architects in making the changes, it delayed our contractor in getting quotes, and it delayed next steps in the process.  It ended up that a couple days delay in one decision ended up delaying the process by 2 weeks.  Arghh!

To be honest, I thought I would feel more happy about getting our building permit, and while this does put a smile on my face it doesn’t make me jump up and down like getting our development permit did.  I guess the difference is that we knew we were going to get the building permit, it was just a matter of when.  I also think that we just have so much work to do, its hard to take a breath to give each other a high five.

Anyhow, we will keep you up to speed on some of the next steps with our brewery in the coming weeks ahead.  Lots of activity and hopefully we can drive this project ahead to start operations sooner rather than later.

Advertisement

Success …. Development Permit! Now what?

Today was a great day in our world:  We received news first thing this morning about the status of our Development Permit that was submitted to the City of Vancouver about 14 weeks ago.  Our permit was approved via rubber stamp by the City, which paves the way for us to move forward with permission to brew beer at our desired location.  In other words, from the City of Vancouver’s point of view, brewing beer in our chosen location is something we can do, should we want to do it.

I often hear that it is important to celebrate your successes, no matter how small, as you need to draw upon these when you are slugging it out in the trenches.  So tonight I have a smile.  Tonight, I feel like the dream of opening my very own craft brewery is one giant step closer to reality.  Tonight, I still feel in control of my own destiny.  Tonight, I feel re-energized and ready for the next challenge that I will face.  Tonight …… well if I keep going on it will soon be tomorrow morning.

While this success is great, we still have other challenges that are right before us.  The most important of those is finding a solution to this electrical issue.  We are underpowered at our space, and we are searching for economical ways around it.  It is painful to know that every conversation you have with electrical engineers and other professionals costs money, but what other options are there?

The latest update on the power is that we should know this week about what options are available, and then we can decide whether or not we want this space.  If we can keep the bill under $100,000, then I think we are going to move forward.  However, if we can’t find a way to keep the bill under this number, then I think we walk away.  Hydro and our electricians are busy scurrying around getting answers.

All the while this is going on, we are still working away on our building permit submission.  We have (rightly or wrongly) assumed that we will find an answer to the electrical issues, and given that we need to have a full set of plans ready for building permits ASAP.  Time is the big enemy here, as every delay in submitting our building permits is another day more that money just goes out the door.  If we can’t get our brewery up and running by August 1st, then we run the risk of needing more loans and lines of credit, and we also run the risk of missing out on the busiest time of year for breweries …. Summer.

Needless to say, with this small win, we are one step closer to making this dream a reality.  Tonight we celebrate, as tomorrow there is even more work to do.

How Important is the Name???

One item that I have grappled with for some time is the name of my brewery.  There seems to be three different avenues people take in naming a brewery, which appear to be popular.

The first is to name the brewery after the owner.  Think R and B Brewing, Phillips Brewing, Hoyne Brewing, and even Molson.

The second is to name the brewery after an area or landmark.  Think Coal Harbour Brewing, Deep Cove Brewers and Distillers, Granville Island, and Stanley Park Brewing.

The third is to name the brewery after nothing in particular.  Think Storm Brewing, 33 Acres Brewing, Bomber Brewing, and Dead Frog Brewing.

There seems to be no rhyme or reason why names are chosen, and some end up being good and others end up being a little less than interesting.  My belief is at the end of the day, a name is not that important.   In my opinion, If you make shit beer, but have a great name, your chances for success are not going to be great.  On the other hand, if you have a shit name, but make great beer, I think you are going to succeed.

I would love to know what people think are good names in the marketplace?  I have my opinions, and for the most part, I think having a variety of names in the marketplace is a good thing.